Maintenance

Instructions - Instruction Labour

Linking Labour Resource requirements to an instruction, gives you the ability to see how many employees are required to do a certain craft type (skill), which will allow for planning the resources that may be required for upcoming projects or tasks.

Ribbon Access:   Maintenance / Projects>   Instructions

  1. The Instructions listing screen will be displayed.
  2. Click on the row of the instruction you wish to link a labour resource requirement to.
  3. Click on Edit.

    Short cut key: Right click to display the Process menu list. Click on Edit.

  1. The Instruction Maintain screen will be displayed.
  2. On the Labour Resource docking panel,
  3. Right click in the Craft text box to display the Process menu list.

Add New Craft

  1. Click on Craft - Add New Craft.

  1. The Select a craft screen will be displayed.
  2. Click on the row of the craft (skill) that you wish to link to this instruction.
  3. Click on OK.

  1. The Craft and Craft Name will populate according to the selection made.

Add Crew and Time

  1. Crew: Click in the text box and type in or use the arrow indicators to select the number of employees that are required to complete this instruction.
  2. Time: Click in the text box and type in or use the arrow indicators to select the total time (in hours) required for this instruction.
    • The example has 1 Technician as required at a total time of 2 hours.
  3. Click anywhere in the Labour Resources data grid to open the next entry line.
  4. Repeat from Step 6, to continue adding the Labour Resources as required.

Save Labour Resource

  1. When you have finished, click on Save.

  1. When you receive notification to confirm that;
    • Instruction : [abbrev/number] saved
  2. Click on OK.

  1. You will return to the Instructions listing screen, click on Back to return to